Platteville Inclusive Playground Committee to Host Playground Design Sneak Peek Event on Thursday, April 21

Playground Equipment First Look Graphic

The Platteville Inclusive Playground Committee presented playground design options to the Common Council on Tuesday, March 22.  Of the four companies that submitted designs, the committee noted that all were accommodating with good equipment to offer.  That being said, the preferred company recommendation was unanimous throughout the Inclusive Playground Committee and the Parks, Forestry and Recreation Committee.  The playground company recommendation was approved by the Common Council at the Tuesday, April 12 meeting.  

Join the Platteville Inclusive Playground Committee on Thursday, April 21 to get a first look at the playground design! 

Platteville Inclusive Playground Tentative Timeline:

  • Fundraising until approximately April 25, 2022  (donations will still continue to be accepted)
  • Order equipment the first week in May 2022. (orders take approximately 16 weeks to get in)
  • City scheduled to select General Contractor for the project on May 10, 2022
  • Tentative Groundbreaking on May 31, 2022. (There are an order of other projects to be done before equipment goes in.)  
  • Playground equipment is estimated to be installed in September of 2022.

Interested in making a donation?  Contact the Platteville Inclusive Playground Committee at plattevilleinclusiveplayground@gmail.com.  For more information about the steering committee and donors, visit www.platteville.org/inclusiveplayground.